Yesterday, Forefront Construction completed the polymer application to the gravel layer in the bunkers on 1, 7, 8, 9, 16 and 18. The cure time on the gravel before sand installation can start is 24 hours. The plan for today is to keep installing gravel in the bunkers that are cleaned out (2,3,4) and this afternoon start sand installation in the bunkers that got sprayed yesterday.