Sunday, January 12, 2014

Bunker Project Status Update

The work on the bunkers is progressing smoothly and on schedule to this point.  As of this morning the removal of old sand and liner, drainage repair and gravel layer installation is complete on holes 16, 18 and 1.  The bunkers on holes 2, 7, 8 and 9 are cleaned out and are ready for drainage completion and gravel layer installation.  Old material removal is taking place on hole 3 presently.  Additional drainage has been added in the right front bunker on 16.  The bunker on 9 and the right side bunker on 7 are receiving additional drainage added as well where none existed.  Once the gravel layer is installed in the first 9 holes of bunkers, the plan is to spray the polymer in those bunkers.  The polymer needs 24 hours to cure before sand installation can happen.

No comments:

Post a Comment